Over the next couple of months, the library will be completing schematic design work and then go into design development for the building addition & renovation project. After that, the architects will need to produce construction documents and then prepare for bid. Below are some of the basic milestones for the project going forward. Please be aware that these dates are tentative. Building projects have a great deal of variability in timing and other circumstances that may force changes to this timeline. Please be patient as this process gets underway, we will provides updates as they become available.
Activity | Time Frame |
Approval of Architectural and Construction Management Contracts | ASAP |
Schematic Design/Design Development | April or May of 2019 |
Procure S&P Bond Rating | April-June 2019 |
Bonds Issued | June 2019 |
Bid Documents Issued | July 2019 |
Bids Received | October 2019 |
Shop Drawings Prepared | December 2019 |
Construction Contracts Completed | December 2019 |
Move Out of Mobile Units | January 2020 |
Demolition | February or March 2020 |
Groundbreaking | February or March 2020 |
Substantial Completion—Addition | March 2021 |
Move to Addition | Substantial Completion + Two Weeks (March or April 2021) |
Grand Opening | July or August 2021 |